The New Mexico Environment Department has updated parts of the food establishment rules that affect permits, renewals, plan review, and reinspections. You will remember that NMRA fought this change. We testified and sent more than 80 letters in opposition to the Environmental Improvement Board. They did not listen to us and passed the regulatory changes unchanged. The main changes are higher late and re-inspection fees, increased plan review fees, and an updated variance fee. Please review your permit expiration date and any upcoming renovation or plan review requirements to avoid extra costs. NOTE: Albuquerque and Bernalillo County have separate food codes.

Fee type Amount
Food establishments, mobile food establishments, servicing areas, and food processing plants $200
Temporary food establishment permit $25 per event
Variance application fee $400
Plan review fee: food establishment, 0–1,000 sq. ft. $300
Plan review fee: food establishment, 1,001–2,000 sq. ft. $600
Plan review fee: food establishment, 2,001+ sq. ft. $900
Plan review fee: food processing plant, 0–1,000 sq. ft. $400
Plan review fee: food processing plant, 1,001–2,000 sq. ft. $900
Plan review fee: food processing plant, 2,001+ sq. ft. $1,400
Late renewal fee $175
Re-inspection fee $500

Other changes

  • Effective date updated: The rule’s effective date changes to October 1, 2026.
  • Variance requests: The agency must act on a variance request within 15 working days after it receives the request and the fee.
  • Plan review fee: If a permit holder or applicant needs plan review, they must submit properly prepared plans and specifications at least 30 calendar days before the work or change that requires approval. Applicants now must also pay the assigned fee rate when submitting plans.
  • More violations can trigger re-inspection: A re-inspection can now be scheduled not only for a priority item violation, but also for a repeat priority foundation or core item violation within the last 25 months.
  • No refund or discount: The rule says there is no discount or refund for fees paid, including when a permit is suspended or revoked.
  • Stricter renewal consequences: If a permit is not renewed and required re-inspection fees are not paid within 30 days, a new permit cannot be issued until the normal requirements are met and the plan review fee is paid.
  • More enforcement costs: Violations of Title 7, Chapter 6 may now also lead to administrative compliance costs, in addition to civil penalties and other remedies.
  • Updated food processing facility record rules: The rule adopts parts of 21 CFR 117 and requires records to be made promptly available to regulators; offsite records are allowed only if they can be provided onsite within 24 hours.
  • Adulterated or misbranded food: The rule keeps the requirement that such products must be reconditioned, condemned, or destroyed under state law.
  • FDA registration for certain processors: Low-acid canned food and acidified food processors must register their plants and file processing information with the FDA.
  • Shellfish standard updated: The state now adopts the 2023 NSSP guide for molluscan shellfish instead of the 2017 guide.
  • Home-based food processing section removed: The old home-based food processing section is deleted from this chapter due to other recently passed legislation regarding home made food.

Message for Members